Clarks - Mall of Dhahran

Full retail fit-out including MEP, flooring and shopfront works.

LocationMall of Dhahran, Dhahran
Client / Contracting PartyApparel Group
Year2026
Duration27 days
StatusCompleted

TA Scope

Full retail fit-out including MEP, flooring and shopfront works.

Main Challenges

  • Delivering multiple trades within a 27-day programme
  • Coordinating civil, MEP and display installation activities
  • Working within mall access and permit restrictions
  • Completing testing and snag closure before opening

Works Completed

  • Site preparation and setting out
  • Partitions, ceilings and finishing
  • Floor installation
  • Electrical, lighting and HVAC coordination
  • Display fixture installation
  • Shopfront works
  • Testing, cleaning and handover