Projects
Calvin Klein - Mall of Dhahran
Fast-track refurbishment and fit-out, client-supplied furniture installation, MEP modifications and shopfront refurbishment.
LocationMall of Dhahran, Dhahran
Client / Contracting PartyApparel Group
Year2026
Duration5 days
StatusCompleted
TA Scope
Fast-track refurbishment and fit-out, client-supplied furniture installation, MEP modifications and shopfront refurbishment.
Main Challenges
- Five-day completion requirement
- Protection of premium existing finishes
- Furniture and MEP interface coordination
- Alignment with the approved brand layout
Works Completed
- Site preparation and rectification
- Electrical and MEP modifications
- Furniture and display fixture installation
- Shopfront refurbishment
- Painting, testing, cleaning and handover